Reporting
Template for Deliverables: provides guidelines for the sections to be included in each deliverable.
The time for our second report is nearly upon, beginning 1st Septemer 2011, please find below some dates for your diaries to help ensure we are prepared and the process goes as swiftly as possible.
Timetable*
Partners receive tables and guidance - 12 August 2011
Deadline for submission of information (Tables and Form C) to Coordinator - 23rd Septemer 2011
Report completed and submitted to Commission October 2011
Submission of Deliverables
We wanted to flag this early, all deliverables due by M36 must be submitted by 31st August 2011For those deliverables that will be submitted late we need to provide the Commission with written justification as to the reason for the delay and the anticipated date of delivery. Any late submission of deliverables/no justification for delays may comprise the next round of funds from the Commission so we ask you to be on top of this.
Useful documents for reporting
Presentation on using FORCEFinancial Guidelines FP7 projects
Grant Agreement Annex II - General Conditions
General Guidance on FP7 Reporting
MEECE Periodic Reports
NEW: The Scientific Report from RP2 is available to download, the report does not include any financial details but this information is available from the Project Office on request.
The Scientific Report from RP1 is available to download, the report does not include any financial details but this information is available from the Project Office on request.